Project Notices

For notices related to the North Campus Infrastructure project, please visit the North Campus Infrastructure Construction notices page.

Construction Notice - CARI Classroom Renovation

Construction Schedule: September 3, 2019 to December 20, 2019
Description of Project: CARI 2nd floor, F-Wing - renovation to add classroom space for the 3D modelling and Visual Arts departments.
Customer Impact: Beginning September 3, 2019, a portion of the parking stalls outside the north entrance of CARI will be fenced off for construction purposes. Work will be contained to the 2nd floor F-wing. General construction activities will be taking place throughout the day, however, any worked deemed noisy will be done outside of normal working hours of the building.
Contractor: Holaco Construction
Consultant: Colborne Group

If you have any questions regarding this construction, please Jhonathan Martinez at (778) 945-6201 or [email protected]

Construction Notice – Student Housing Electrical Service Upgrade

Construction Schedule: August 12, 2019 to February 2020
Description of Project: Student Housing Electrical Service Upgrade is the first area of Burnaby's South Campus to be upgraded to BC Hydro's new standard of connection and delivery. Similar to the North Campus Infrastructure Project, this is an essential upgrade to electrical infrastructure that improves reliability and while advancing the institute's sustainability goals by allowing for improved delivery and management of energy.
Customer Impact: Beginning August 12, 2019, the construction zone along Fairey Street and a portion of White Avenue will be fenced off for site preparation works. Construction impacts will be updated as the project progresses. Please note, White Avenue will be subject to controlled access (1-lane south bound traffic only) adjacent to Lot P6 in the upcoming weeks.
Contractor: PCL

If you have any questions about this scheduled construction, please James Woo at (778) 945-6129 or [email protected]

Construction Notice – Renovations to SW01/1022

Construction Schedule: July 4th, 2019 to September 15th, 2019
Description of Project: Renovating BSW01/1022, 1026, 1028 and converting private office 1024 to open office area
Customer Impact: Construction noise and dust – through working on the area and hoarding will make the corridor narrow
Contractor: Finlink Construction Ltd.
Consultant: DA Architects + Planners

If you have any questions about this scheduled construction, please Somy Peykani at 111-432-8651 or [email protected]

Construction Notice – Renovations to SW01/1018 and 1019

Construction Schedule: July 4th, 2019 to September 15th, 2019
Description of Project: converting two storage rooms 1019 and 1018 to the transportation and grounds office
Customer Impact: Construction noise and dust – through working on the area and hoarding will make the corridor narrow
Contractor: Finlink Construction Ltd.
Consultant: DA Architects + Planners

If you have any questions about this scheduled construction, please Somy Peykani at 111-432-8651 or [email protected]

Construction Notice – NE16 Re-roofing

Construction Schedule:  May 13, 2019 to August 30, 2019
Location:  NE16 Roof
Description of Project:  Removal and replacement of the existing roofing membrane
Customer Impact:  Noise, temporary electrical, Heating Ventilation and Air Conditioning (HVAC) shutdowns
Contractor:  PCL

If you have any question about this scheduled construction, please Jhonathan Martinez at 778-945-6201 or [email protected]

Construction Notice – SE16 Windows & HVAC Renovation

Construction Schedule:  June 1, 2019 to August 29, 2019
Location:  SE16 rooms
Description of Project:  Upgrading the windows and HVAC system to meet current Codes, industry best practices, and Roommeme Technical Standards
Customer Impact:  Clinic closure, office closure and minor noise
Contractor:  Turner Construction Ltd.

If you have any question about this scheduled construction, please Jhonathan Martinez at 778-945-6201 or [email protected]

Construction Notice – SE02 Refrigeration Retrofit

Construction Schedule:  June 24, 2019 to August 29, 2019
Location:  SE02 kitchen
Description of Project:  Remove and replace existing refrigeration units including associated architectural, mechanical and electrical work. Installation of new interior refrigerators.
Customer Impact:  Use of temporary refrigeration units during construction
Contractor: Finlink

If you have any question about this scheduled construction, please Jhonathan Martinez at 778-945-6201 or [email protected]

Construction Notice - SW02 Elevator Refurbishment

Construction Schedule: From June 3, 2019 to August 23, 2019
Description of Work: Refurbishment and/or replacement of major hardware and control equipment, interior finishes and all items required to meet current code requirements.
Contractor: Holaco Construction Ltd. / Richmond Elevator
Consultant: GUNN Consultants
Customer Impact: Minor noise during the construction and SW02 elevator will be out of service from July 1 to August 15, 2019.

If you have any question about this scheduled painting, please Tim Wong, Senior Project Coordinator, at 111-432-8762 or [email protected]

Construction Notice - SW01 Building (Old Building Portion)-Exterior Wall Cleaning and Improvements

Construction Schedule: June 7 to August 31, 2019
Location: SW1 Building on the Burnaby Campus
Description of Project: Exterior walls low pressure power washing and cleaning, minor concrete crack repair, existing sealing and flashing replacement. Scope of work includes work under environmental procedures for hazardous materials such as asbestos and lead.
Customer Impact: The work will be staging and starting in sections from low level first and to move up side of the building exterior. Occupancies inside building within and close-by working section are advised to close the windows and curtains inside the building. Minor noise will occur during the existing sealing removal and low pressure wash. Sections of the pathway around the building will be taped off due to work at above.
Contractor: Finlink Construction
Consultant: Morrison Hershfield

If you have any question about this scheduled construction, please Tim Wong at 111-432-8762 or [email protected]